INITIAL DEVELOPMENT SCHEDULE

                                                             

                                                                                                                                   12/9/10

 

Week of

Schedule

August 23, 2010

Clearing Limits of Phase 1A

Plan Flagged in Field – 8-23-10

Meeting with Adjoining Burgundy Woods HOA – 8-25-10

 

 

 

August 30, 2010

Final Site Plan Approval – Approved 8-30-10

Site Development Permit Issued 9-1-10

Meeting with Governor's Grove HOA – September 1, 2010

 

 

 

September 13, 2010

Application for VDOT Entrance Permit – 9/14/10

Initial Pre-Construction Meeting to Review Clearing Limits –

Walk of Clearing Limits for Phase 1A Erosion Controls with Fairfax County and Urban Forestry – 9/15/10

Initiate Phase 1A Tree Protection - 9/17/10

Site walk with Burgundy Woods & Governor's Grove HOA – 9/18/10

 

 

September 20, 2010

Complete Phase 1A Tree Protection Installation – 9/23/10

 

 

 

September 27, 2010

Meeting with Burgundy Civic Association – 9/27/10

Inspection by Fairfax County of Tree Protection Measures – 9/29/10

 

 

 

October 4, 2010

Received VDOT Entrance Permit 10/4/10

Initiate Clearing Operation Onsite to Install Phase 1A Erosion Control Devices

 

 

October 25, 2010

Complete Phase 1A Clearing and Schedule Inspection

Receive Final Inspection by Fairfax County of Erosion Control Devices

Special Inspection Meeting for H-Pile

Building Permit Issued 10/28/10

 

 

November 8, 2010

Initiate installation of H Piles – 11/9/10

Install Water Monitoring Wells – 2 Wells Installed

 

 

December 6, 2010

Lower H-Pile Wall 50% Complete

 

 

January 3, 2011

Complete Lower H-Pile Wall

 

 

February 7, 2011

Complete upper H Pile Wall Installation

Receive Final Certification by Geotech Engineer of H Piles

Flag Clearing Limits for Phase 1B Erosion & Sediment Control Devices

 

 

February 14, 2011

Hold Pre-Construction Meeting prior to Installation of Phase 1B Tree Protection and Erosion Control Devices. Initiate Phase 1B Clearing

 

 

President's Letter

Board Meeting Minutes

Annual Meeting Minutes

Newsletter

Neighborhood Watch Newsletter

Fairfax County Neighborhood Watch Notices

Documents/Forms

Fairfax County Rules on Pets - Leashes and Cleanup

Contact Information
Website Comments/Suggestions